A low cement castable heating schedule has one job: let water leave the lining faster than it turns to steam inside it. Miss that balance and the lining you just paid to install cracks or sheds slabs on the first heat-up, before it ever sees process temperature.
For most single-component low cement castable linings the working sequence is short. Cure for at least 24 hours. Raise the hot face to 149°C (300°F). Hold there for 1.5 hours per 25 mm of thickness, capped at 8 hours. Climb at 28°C/h (50°F/h) to operating temperature or 540°C (1000°F), whichever comes first, and open the rate up above 540°C only if the lining is thin enough to take it.
Two mistakes cause most dry-out failures on site: compressing the 149°C hold because the shutdown is late, and pushing the burners early because the thermocouple looks slow. Both put steam pressure ahead of the lining’s green strength.
Quick answer
Key takeaways
Contents
Water sits in a cast lining in two forms, and the two leave at different temperatures. Free water — the mixing water that never reacted — starts moving out around 100°C. Chemically combined water is bound inside the calcium aluminate hydrates that give a low cement castable its green strength, and it does not release until roughly 250°C.
The risk is not the temperature, it is the rate. When vapour is generated deeper in the section faster than it can travel to the surface, pressure builds until it exceeds what the partly dried lining can hold. The result is explosive spalling: sections of lining separate and, in the worst cases, blow off the shell.
That is why published schedules for LCC and ULCC are built around holds rather than a straight ramp. The hold is the window that lets moisture migrate out instead of flashing inside.
The schedule assumes a few conditions that are easy to miss on a shutdown.
Cure first. A minimum of 24 hours above 10°C, kept damp, gives the cement hydrates time to form. Heating before that locks in a weak surface that later shows up as crumbling. Where the programme allows, 48 to 72 hours beats the minimum.
Check the weep holes. Cast sections are commonly drilled or formed with vent paths. If they are blocked with fines or mortar, vapour has nowhere to go but back into the lining.
Place thermocouples properly. Measure at the refractory hot face, and at several points rather than one — a single probe hides cold spots. Where the shell allows, a temporary thermocouple on the cold face is worth the trouble, because it is the only way to confirm heat has reached the back of the lining.
Confirm the ambient range. Published schedules assume roughly 16–32°C around the unit. Outside that, work to a more conservative schedule.

For single-component linings up to 230 mm (9 in) thick, the sequence below is the published industry procedure. Temperatures are measured at the hot face.
The 8-hour ceiling is a cap on one hold, not a shortcut for thick sections. A 200 mm lining works out to 12 hours at the 1.5 h per 25 mm rate; the schedule caps that hold at 8. Where the cap bites, plan a longer programme — not a faster ramp.
Thick sections get more hold points and one considerably slower band. For single-component linings over 230 mm (9 in):
The 232–315°C band is the slowest part of the whole programme at 14°C/h, and it is exactly where chemically combined water comes out of the hydrates. There is no shortcut through it.
Do the arithmetic before committing to a date. On a 300 mm lining each hold runs 12 hours, so the full sequence is a multi-day programme. Plan the shutdown around the dry-out.
| Stage | Range | Rate | Hold at top of range |
|---|---|---|---|
| Cure | Ambient, above 10°C | — | 24 h minimum; 48–72 h preferred |
| First ramp | → 149°C | 28°C/h for linings over 230 mm; no fixed rate below that | 1.5 h per 25 mm, max 8 h (up to 230 mm) 1 h per 25 mm (over 230 mm) |
| Second ramp | 149 → 232°C | 28°C/h | 1 h per 25 mm |
| Third ramp | 232 → 315°C | 14°C/h — slowest band | 1 h per 25 mm |
| Fourth ramp | 315 → 540°C | 28°C/h | 1 h per 25 mm |
| Above 540°C | 540°C → operating | 56°C/h (up to 152 mm) 28°C/h (152–229 mm) |
— |
| Cool-down | Operating → ambient | ≤ 56°C/h | — |
All temperatures in this table are measured at the hot face of the lining. Holds at 232°C, 315°C and 540°C apply to linings over 230 mm; thinner linings run straight from the 149°C hold to operating temperature or 540°C.

A schedule on paper does not move vapour. Air does.
Burner sizing and position determine whether the lining heats evenly or develops a hot spot that dries one patch while the rest stays wet. Exhaust position matters just as much: vapour has to leave the furnace, and below 300°C the doors and dampers should be open so it can. A closed furnace traps steam against the lining you are trying to dry.
Air volume and velocity through the unit are the variables most often skipped. Still air over a wet lining stalls drying no matter how correct the ramp is.
Confirm the weep holes are open before you start; a blocked vent turns the section into a closed vessel. Where the budget allows, a dry-out specialist earns their fee here — burner layout and exhaust routing are what a schedule table cannot do for you.
Ultra low cement castables are denser and less permeable than standard LCC. That is precisely what makes them resist slag penetration, and precisely what makes them harder to dry: there is less open porosity for vapour to escape through, so internal pressure builds sooner for a given heating rate.
In practice, treat the LCC figures above as a floor rather than a target. Take the slower end of every rate and extend holds rather than trimming them. The 232–315°C band deserves the most caution, because it is where combined water is released and where a dense matrix resists it most.
No-cement castables behave differently again. The bonding system is not hydraulic, so both the cure behaviour and the critical temperature band shift away from the figures here. See the grade-specific ULCC dry-out precautions, and defer to the TDS for the product actually installed.

| Symptom | Likely cause | What to do |
|---|---|---|
| Steam still venting above 300°C | Moisture trapped deeper in the section | Hold temperature until steaming stops. Do not raise. |
| Map cracking on the surface | Initial ramp too fast | Slow to 25°C/h or less below 300°C. |
| Deep cracking through the thickness | Gradient too steep across a thick section | Longer holds at 149°C and 315°C; verify with an embedded thermocouple. |
| Slabs separating or blowing off | Ramp too fast below 300°C; pressure above green strength | Stop and restart from the beginning. Check weep holes and exhaust path. |
| Crumbly, weak surface | Cured under 24 h, or allowed to dry out during cure | Re-cure before heating; keep damp above 10°C. |
| Heat or power lost mid-hold | Interruption of unknown duration | Restart the schedule from the beginning. |
The restart rule is unpopular but worth stating plainly. Once heat is lost partway through a hold, the temperature profile is unknown, and finishing that hold does not prove the interior dried. Restarting costs a day; spalling costs the lining.
Never let a partly dried lining drop below 100°C. Condensation re-wets the section and the dry-out has to start again from the beginning.
Cooling gets less attention than heating and can do comparable damage. Let the lining cool naturally and keep the rate at or below 56°C/h (100°F/h).
If the unit is not going straight into service, hold at operating temperature before the cool-down starts — a minimum of 1.5 hours per 25 mm of thickness, capped at 8 hours. That hold evens out the section temperature and reduces the gradient the lining sees on the way down.
No. Every figure in the schedule is set by how fast vapour can travel through the lining, and that does not change because the programme slipped. Compressing a hold is the single most common cause of explosive spalling. If the date cannot move, the realistic options are a temporary lining, a faster-curing grade on the next reline, or more burners and airflow rather than a steeper ramp.
Use a thermocouple on the cold face if the shell allows one. The lining is dry when the cold-face temperature stops climbing and stabilises during a hold, which shows heat has penetrated the full thickness and free water has gone. Visible steam stopping is a useful secondary sign, but on its own it only tells you about the surface.
Often yes, but only if they can hold a low, stable output. Main process burners are usually sized to reach operating temperature quickly, and most cannot be turned down far enough to sit at 149°C for eight hours without cycling. Cycling is worse than a slightly higher steady rate, because it repeatedly pushes heat into a lining that has not finished drying.
A thin patch under about 50 mm can usually follow a shortened version, because the moisture has a short distance to travel. Treat anything deeper as a full lining and run the complete schedule by thickness. The surrounding old lining also matters: it will absorb heat and can mask how wet the repair actually is, so measure at the patch rather than at the sound refractory next to it.
Let it drain and dry at ambient temperature before you start, and extend the first hold rather than shortening it. A saturated lining carries far more free water than the schedule assumes, so the 149°C hold is doing more work than usual. If the surface has been washed out or the cement paste has been leached away, the affected area needs replacing rather than drying.
The schedule is not complicated: cure, hold at 149°C, climb at 28°C/h, respect the slow band through 315°C, cool gently. What separates a lining that reaches full campaign from one that fails on first heat-up is discipline in the holds, not knowledge of the numbers.
Every figure on this page comes from published industry procedures for low and ultra-low cement castables. Your grade’s own TDS takes precedence over all of them, and where the two disagree, follow the TDS. If you need the schedule for the specific grade you are installing, ask the manufacturer for the grade TDS with the product name and lining thickness.
Where these figures come from. The hold points, ramp rates and per-thickness hold rules in sections 3, 4 and 5 follow the published heating procedure for low, ultra-low and no-cement castables issued by Resco Products (Technical Information 104). General drying practice in sections 2, 6 and 8 reflects widely used dry-out guidance: minimum 24-hour cure, free water released near 100°C, combined water near 250°C, keep below 50°C/h under 500°C, vent below 300°C, hold whenever steam is visible, and restart after any loss of heat. These are starting points for planning, not a substitute for the product TDS.
Ultra low cement castable is the top of the low-cement family: a monolithic refractory formulated with under 1.0% CaO, against 1.0–2.5% for a standard LCC. That extra reduction in lime — achieved with 2–5% calcium aluminate cement, more reactive alumina and silica fume, and a tighter dispersant package — is what gives a ULCC its signature traits: higher bulk density, higher hot strength, and markedly better resistance to slag penetration. When a lining faces molten slag or alkali vapour at close range, this is the grade that holds the line longest.